CASE STUDY — COMMERCIAL CASE - NAPLES, FL

Mont Claire at Pelican Marsh

The residents at Mont Claire needed over 200,000 square feet of concrete tile roofing replaced quickly, and CWC delivered a safe, efficient, and expertly managed roofing project that met the tight schedule and restored the community’s roofs on time.

> > Request Free Inspection

The Challenge

A time-sensitive roofing project for a large HOA community

From the very beginning, timing was critical at Mont Claire. The HOA’s insurance was set to expire at the end of January, and the property owners needed over 200,000 square feet of concrete tile roofing replaced quickly to avoid skyrocketing insurance costs, all while maintaining safety and minimizing disruption to residents throughout the community.

The Mont Claire project presented significant challenges due to its scale and the tight schedule. Crews had to work efficiently across multiple buildings while minimizing disruption to residents and maintaining clear access throughout the community.

Adding to the complexity, the roofs required careful removal and replacement of over 200,000 square feet of concrete tile, along with 1,700 lineal feet of stucco and flashing. Debris control, safety, and proper coordination were critical to keeping the project on track and ensuring the well-being of both residents and crew members.

CWC responded with a precision-focused approach, maintaining strict safety protocols while coordinating work zones to minimize disruption to residents. The team ensured that every step of the project was clean, organized, and respectful of the community’s environment, even with multiple buildings and a tight schedule.

Despite these logistical complexities, CWC’s experience with large multi-family projects allowed the team to adapt seamlessly, adding manpower and resources as needed to stay on schedule. The roofs were installed efficiently and safely, earning county inspections and engineering approvals without issue, and giving residents confidence in the process and results.

THE SOLUTION

CWC delivered a safe, efficient, and timely roofing project

With careful planning, smart scheduling, and tight safety protocols, CWC completed the Mont Claire roofing project on schedule despite initial material delays and a tight deadline. Our crews worked efficiently across multiple buildings, maintaining clean work zones and minimizing disruption to residents. By leveraging our experience, manpower, and constant communication with the HOA, CWC delivered a high-quality roofing solution that restored the community’s roofs while giving the client confidence in our reliability today and for future projects.

Fast, precise work with minimal disruption

Time management and careful planning were critical to the Mont Claire project. The CWC project management team coordinated every step of the roof replacement to ensure the work was completed safely, efficiently, and with minimal impact on residents.

Thanks to our experience and detailed project planning, CWC successfully completed the removal and replacement of 211,000 square feet of concrete tile roofing, along with 1,700 lineal feet of stucco and flashing, restoring the functionality and appearance of all buildings.

To achieve these results on schedule, CWC deployed a skilled crew of up to 50 workers, used specialized equipment including mobile dumpsters and large forklifts, and maintained strict safety protocols on-site every day. The project was completed efficiently, leaving the community with durable, high-quality roofs that meet professional standards.

Prioritizing the well-being of residents and crew

With so many moving parts and a large number of residents coming and going daily, safety was the top priority throughout the Mont Claire project. CWC maintained a constant focus on protecting both the residents and our crew members during every stage of the roofing work.

We implemented safety perimeters around each building, stationed monitors on the ground, and used cones to guide traffic. All crew members working on the roofs were roped and harnessed according to OSHA standards, ensuring that everyone — residents and workers alike — remained safe while allowing the project to proceed efficiently and without incident.

Roofs built to last

At Mont Claire, CWC didn’t just replace the old roofs — we installed a durable roofing system designed to protect the buildings for decades. Using high-quality materials, including a 2-ply Polyglass underlayment system, new flashings, and concrete tile roofing, we ensured each roof provides long-term protection against storms, leaks, and general wear.

Our experienced superintendents oversaw the project to make sure all systems were installed to code and according to manufacturer specifications. Residents and the HOA can now feel confident that their roofs are not only visually seamless but also built to last, providing reliable, worry-free protection for years to come.

Keeping clients informed every step of the way

Large projects like Mont Claire come with logistical challenges, tight timelines, and unexpected hurdles, including material delays and weather complications. Luckily, CWC’s team has the experience and know-how to adapt to any job site, ensuring work progresses smoothly and efficiently.

Throughout the project, we maintained daily communication with the HOA President and board members, keeping everyone informed of schedules, progress, and any adjustments. Our field management team adapted quickly to challenges, ensuring the project stayed on track, met deadlines, and fulfilled the client’s expectations for safety, quality, and timing.