Zumbehl Commons needed a reliable roofing solution that minimized disruption to daily business operations, and CWC delivered a fast, clean, and efficient EPDM overlay that restored the roof’s functionality while keeping traffic, noise, and mess to a minimum.
The Zumbehl Commons roof replacement required careful planning due to the busy commercial environment. Crews had to work efficiently without blocking parking areas, interfering with customer traffic, or creating hazards in the plaza.
Fortunately, the existing roof was still in good condition but nearing the end of its lifespan. This required careful preparation to ensure the new EPDM overlay was installed correctly without disturbing the building’s operations, protecting both the structure and the people using the plaza daily.
CWC responded with a precision-focused approach, maintaining strict safety protocols while coordinating work zones to avoid interfering with customer traffic. The team ensured that every step of the EPDM overlay installation was clean, organized, and respectful of the plaza’s environment.
Despite the logistical complexities of working in a busy commercial space, CWC’s experience with similar projects allowed the team to adapt seamlessly. The roof was installed efficiently and safely, minimizing disruption to businesses and customers while delivering a high-quality, long-lasting roofing solution.
Fast, precise work with minimal disruption
Time management and careful planning were critical to the Zumbehl Commons project. The CWC project management team coordinated every step of the EPDM overlay installation to ensure the work was completed safely, on schedule, and with minimal impact on the businesses and customers in the plaza.
Thanks to our experience and detailed project planning, CWC successfully completed the installation of the new EPDM roofing membrane over the existing roof, restoring its functionality while avoiding a full tear-off and minimizing labor and material costs.
To achieve these results within the required timeframe, CWC deployed a skilled crew, used specialized equipment, and maintained strict safety protocols on-site each day. The project was completed efficiently, leaving the commercial building with a durable, long-lasting roof that meets professional standards and ensures continued operations without disruption.
Prioritizing the safety of building occupants and crew
With a busy commercial plaza full of daily traffic, safety was the top priority throughout the Zumbehl Commons project. CWC maintained a constant focus on protecting both customers and our crew members during every stage of the EPDM overlay installation.
We implemented safety perimeters around the work area, stationed monitors to guide foot and vehicle traffic, and ensured all crew members were properly roped and harnessed when working on the roof. These precautions allowed the project to proceed efficiently while keeping everyone on-site safe and minimizing any disruption to the plaza’s operations.
Roofs built to last
At Zumbehl Commons, CWC didn’t just replace the aging roof — we installed a durable EPDM overlay designed to protect the building for years to come. Using high-quality materials and proper installation techniques, we ensured the roof provides long-term protection against weather, wear, and potential water intrusion.
Our experienced superintendents oversaw the project to make sure all systems were installed to code and according to manufacturer specifications. The building owner can now feel confident that the roof is not only fully functional but also built to last, providing a reliable, worry-free solution for the plaza.
Keeping clients informed every step of the way
Large projects like Zumbehl Commons come with logistical challenges, tight timelines, and unexpected hurdles, including coordinating work around daily business operations. Luckily, CWC’s team has the experience and know-how to adapt to any commercial job site, ensuring work progresses smoothly and efficiently.
Throughout the project, we maintained daily communication with the property management team, keeping everyone informed of schedules, progress, and any adjustments needed. Our field management team adapted quickly to challenges as they arose, ensuring the project stayed on track and met the client’s expectations for safety, timing, and quality.